5/26/2026
Irrigation season is rolling right along! Our water allocation for our project water is at 70%. As a rough guess that will keep the system running to mid July. The Adjudicated water is subsiding in the river pretty fast.
Today adjudicated water priorities:
A shares 80%
B shares 56%
C shares 0%
D shares 0%
The majority of the water being used is Project water. That being the case the Florida Water Conservancy District will calculate project water balances at the end of the month and water cards will be sent out.